Terminal Manager Cockpit

Sohar — the six questions I must be able to answer at any moment

Period September 2026
Day 16 of 22 working days
Illustrative figures

1 · Commercial

Are we making money this month?

94% of budgeted margin −6% vs plan
Throughput, month to date128,400 MT
Cost per MTOMR 1.41
Overtime as % of labour11.8%
Revenue at risk (disputes)OMR 18,200
Watch: overtime is the whole gap. 11.8% against a 9% norm is roughly OMR 21k on the month — almost exactly the margin shortfall.

2 · Safety

Are we safe, and do we see it coming?

41 days LTI-free no incidents
Near misses reported14
Open findings23
Open > 30 days7
Stop-works this month2
Act: seven findings older than thirty days is the leading indicator. Incidents follow ageing findings, not falling LTI counts.

3 · Customer

Are we doing what we promised?

87% of norm productivity −13%
Steel coils
96%
Aluminium
91%
Limestone
82%
Project cargo
71%
Root cause, month to date: waiting on lashing 83 hrs · equipment 31 hrs · weather 19 hrs · awaiting cargo 12 hrs. Lashing is two thirds of all lost time and is not a capacity problem.

4 · Assets

Will the equipment let us down?

92% fleet availability +2% vs last month
Units down now3 of 38
Breakdowns this month11
Overdue planned maintenance5
Critical spares below minimum4
Forward look: two reach stackers reach end of economic life within eighteen months. Capex case needs to be in before the budget round, not after it.

5 · People

Do we have the people, today and next year?

88% of required manning 6 short
Absence rate4.2%
Certified crane operators14 (need 16)
Certificates expiring < 90 days9
Retiring within 24 months5
Watch: the crane operator shortfall is what drives the overtime in tile 1. These two numbers are the same problem seen twice.

6 · Improvement

Is the change agenda moving?

5 of 8 goals on track 2 at risk, 1 behind
JanProgress against programme planSep
Lashing turnaroundbehind
Supervision modelon track
Gate and VBS slotsat risk