Late Start / Early Finish — what our own reports already record
“Late Start / Early Finish (Hrs)” is a standing column in all four of our
productivity report templates — Break-Bulk, Bulk, RoRo and Rev.04 — filled in
shift by shift at the quay. These are the totals it has been carrying.
1,658
crane-hours lost
Equivalent to 207 full eight-hour crane shifts. Total across 2024–2026.
54.9%
of all vessel-shifts carry a late start or early finish
12.1%
of all recorded delay time, of 13,687 h logged
16,460
crane-shift records behind these figures, from 1,267 reports
Break bulk — where the delay hours go
Hours lost per cause, 2024–2026, of 2,373 h total delays. Late start / early finish
is the second largest cause — and the largest one that needs no counterparty to fix.
Delay due to CSO
1,081 h · 45.5%
Late Start / Early Finish
651 h · 27.4%
Idle Time
299 h · 12.6%
Open / Close Hatches
117 h · 4.9%
Crane Break Down
114 h · 4.8%
Lashing, Choking, Securing
74 h · 3.1%
Crane Shifting
25 h · 1.1%
Shifting Cargo
11 h · 0.4%
Waiting For Cargo Shipper
2 h · 0.1%
Worst on RoRo and break bulk
Late start / early finish as a share of that cargo type’s total delay hours.
RoRo — 1 of 9
47.4%
Break bulk — 2 of 9
27.4%
Rev.04 — 4 of 12
8.8%
Bulk — 6 of 9
7.8%
Improved in 2025, rising again in 2026
Share of crane-shift records carrying a late start or early finish.
63.6%
37.1%
45.1%
202420252026 YTD
This is not one crew. The pattern is flat across all three shifts —
day 48.0%, afternoon 45.3%, night 50.3% — which points at handover and gang
allocation rather than at any single team.