Subject: Re: Start and stop times -- what our own reports already record Attachment: late-start-onepager.pdf Suggestion: copy everyone who received the earlier overview. Tom raised project sustainability, which makes this a group topic rather than a one-to-one, and it saves having the same exchange four more times. --- Hi Tom, Following up on my earlier reply. Rather than wait, I went back through what we already hold. "Late Start / Early Finish (Hrs)" is not a concept I introduced for this procedure. It is a standing column in all four of our productivity report templates, filled in shift by shift at the quay. Across 1,267 reports from 2024 to 2026 that gives us 16,460 crane-shift records. They show a late start or early finish in 55% of all vessel-shifts, totalling 1,658 crane-hours -- the equivalent of 207 full crane shifts, and 12% of all the delay time we log. On break bulk it is the second largest delay cause; on RoRo the largest. It is flat across day, afternoon and night, so it is not one crew. The one-page breakdown is attached, including what the figures do not prove. So we were already recording it, and we already knew the pattern. What we have never had is where and why, case by case. That is the point of the procedure: it separates late start from early finish, puts a reason code against each gap, and tells us whether the cause is something we can actually fix. Today we can count the hours. We cannot act on them. Worth being honest about the other half of it: we see it on the quay as well, and we as GSVs mostly let it pass. I include myself in that. Not out of unwillingness -- nothing is fed back, so nobody has to say anything, and a late start leaves no trace by the end of the shift. I would also note that this is the largest delay category sitting entirely within our own control. "Delay due to CSO" is bigger, but it needs a counterparty to resolve. This one does not. So my proposal is to start recording now and bring the first weeks of live data to the 21st. Then the meeting is not about whether the problem is real. It is about what the numbers tell us to change, and whether the reason codes match what the clerks actually see -- which we can only find out by running it. Kind regards, Leon